Which of these is NOT one of the three methods of communication that will be documented in a communication plan?
A) Push methods
B) Virtual methods
C) Interactive methods
D) Pull methods
Correct Answer:
Verified
Q20: A project manager must use effective communications
Q21: A project communications matrix includes all of
Q22: The sponsor,project manager and team can establish
Q23: The "act" part of the PDCA cycle
Q24: The final item to be recorded on
Q26: A project communications plan generally includes all
Q27: In order to plan for a project
Q28: _ is the process of the project
Q29: In the project communications matrix,all of the
Q30: The stakeholder register information can be used