____ was originally developed in the late 1950s to meet the need of the rapidly expanding engineering projects associated with government acquisitions such as weapons systems.
A) GANTT
B) PERT
C) CPM
D) WBS
Correct Answer:
Verified
Q31: Which of the following is NOT a
Q57: The three levels of planning are strategic
Q98: The principle of management dedicated to the
Q99: Which of the following is a project
Q101: In the WBS approach,the project plan is
Q102: The job of a(n)_ is to marshal
Q104: The _ community articulates and communicates organizational
Q106: _ is the process of achieving objectives
Q107: The _ diagramming technique uses simple bar
Q108: The CNSS Security model known as the