The Grand Performance Hall is in the process of remodeling and is scheduled to open for business after being closed for 50 years.As part of the remodeling,it is installing a new sound system.The sound system is to be installed by Sound Systems,Inc.on or before April 10.Opening night of the hall is May 1.The contract states that "time is of the essence" because of the opening-night deadline.Sound Systems has some financial difficulties and doesn't deliver the system until April 20.Grand Hall refuses to accept it,and Sound Systems sues.What will be the result?
A) Grand Hall wins;the contract date was strictly enforceable.
B) Sound Systems wins;the contract was substantially performed.
C) Grand Hall wins;there was commercial frustration.
D) Sound Systems wins;there was a true impossibility.
Correct Answer:
Verified
Q22: The law strongly prefers to apply the
Q23: When one party breaches a contract,the discharged
Q24: What is the key to all conditional
Q25: The distinction between a condition precedent and
Q26: Harry agreed to pay $100 to rent
Q28: Dana hires Paris to paint a portrait
Q29: Statutes of limitations
A)define how much money the
Q30: Jackie hires Charles to lay new carpet
Q31: Ron operates a garbage pickup business.He contracts
Q32: Mary contracted to buy 100 table lamps.Under
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents