Solved

Max and Lew Have Entered into a Contract for Lew

Question 55

Multiple Choice

Max and Lew have entered into a contract for Lew to paint Max's house.The contract specifically states that the job was to be completed by August 25.Lew completes the job on August 26.Max has suffered no loss due to the delay.The job was otherwise done exactly to all contract requirements and specifications.If Max sues Lew for breach of contract due to the missed completion date and if the courts were to award damages,what type of damages would most likely be awarded?


A) punitive damages
B) consequential damages
C) restitution
D) nominal damages

Correct Answer: