The CRP system converts tentative planned shop orders into standard hours of load by ______.
A) assessing the levels of inventory of finished product,given the availability of raw materials
B) multiplying each period's production quantity requirements by standard labor or equipment requirements per unit,or both
C) averaging the availability of resources per production hour
D) basing the calculations on the production volume from the preceding production period
Correct Answer:
Verified
Q66: Which of the following is the primary
Q67: When we use lot splitting,we _.
A)divide a
Q68: In the context of a CRP system,a
Q69: An advantage of infinite loading is that
Q70: Which of the following is FALSE about
Q72: CRP systems,like MRP systems,are most useful for
Q73: If it is not possible to increase
Q74: The goal of CRP is to regulate
Q75: If a master schedule has to be
Q76: In capacity requirements planning,we project or estimate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents