If the most optimistic time for completing an activity is 3,the most likely time is 6,and the most pessimistic time is 9,then the estimated time for the activity is ______.
A) 6
B) 3
C) 8
D) 21
Correct Answer:
Verified
Q86: If the standard deviation is 6.5,the Z
Q87: If the standard deviation is 3.4,the Z
Q88: If the most optimistic time for completing
Q89: If the standard deviation is 6.2,the Z
Q90: If the most optimistic time for completing
Q92: If the standard deviation is 3.5,the Z
Q93: If the standard deviation is 2.7,the Z
Q94: If the most optimistic time for completing
Q95: If the standard deviation is 4.5,the Z
Q96: If the most optimistic time for completing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents