Which of the following correctly pairs the terminology used in the earned value management (EVM) method with its description?
A) schedule performance index: the earned value to date divided by the planned value of work scheduled to be performed (EV/PV)
B) cost performance index: the earned value divided by the planned cumulative cost of the work performed to date (EV/AC)
C) both A and B are correct
D) neither A nor B is correct
Correct Answer:
Verified
Q21: Establishing the project's baseline requires _.
A)the work
Q22: The slope for each activity gives _.
A)combinations
Q23: In considering whether we should crash a
Q24: Projections about how much the project will
Q25: Which one of the following is a
Q27: In project management,PERT (program evaluation and review
Q28: Project overhead costs _.
A)are also known as
Q29: The proportion of the total budget allocated
Q30: The SPI is _.
A)the stochastic performance index
B)the
Q31: The cost of the project is given
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents