______ is a dynamic sequencing rule that gives priority to those jobs that most urgently need work so that orders can be completed by the due date and shipped on schedule.
A) First come,first served
B) Shortest processing time
C) Critical ratio
D) Earliest due date
Correct Answer:
Verified
Q21: _ are simple decision rules that are
Q22: Jobs are ranked according to their due
Q23: A scheduling process used to determine the
Q24: Schedules may have to be revised frequently
Q25: The _ rule can be applied for
Q27: In reality,most businesses generally use _.
A)a combination
Q28: The assignment method is a special case
Q29: The job is behind schedule when _.
A)CR
Q30: A scheduling process used to determine in
Q31: The formula for calculating critical ratio is