In Designing Control Charts,companies Usually Use ______

Question 40

Multiple Choice

In designing control charts,companies usually use ______.


A) two standard deviations because narrower control limits may a lead a manager to erroneously conclude that the process is out of control when in fact the variation that led to the points falling out of the control limits was purely random
B) two standard deviations because broader control limits may a lead a manager to erroneously conclude that the process is out of control when in fact the variation that led to the points falling out of the control limits was purely random
C) three standard deviations because narrower control limits may a lead a manager to erroneously conclude that the process is out of control when in fact the variation that led to the points falling out of the control limits was purely random
D) three standard deviations because broader control limits may a lead a manager to erroneously conclude that the process is out of control when in fact the variation that led to the points falling out of the control limits was purely random

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents