In designing control charts,companies usually use ______.
A) two standard deviations because narrower control limits may a lead a manager to erroneously conclude that the process is out of control when in fact the variation that led to the points falling out of the control limits was purely random
B) two standard deviations because broader control limits may a lead a manager to erroneously conclude that the process is out of control when in fact the variation that led to the points falling out of the control limits was purely random
C) three standard deviations because narrower control limits may a lead a manager to erroneously conclude that the process is out of control when in fact the variation that led to the points falling out of the control limits was purely random
D) three standard deviations because broader control limits may a lead a manager to erroneously conclude that the process is out of control when in fact the variation that led to the points falling out of the control limits was purely random
Correct Answer:
Verified
Q35: The most frequently used control charts for
Q36: A control chart _.
A)should be used frequently
Q37: Common cause variations are _.
A)the consequence of
Q38: A control chart _.
A)shows the correlation between
Q39: Samples are used because measuring every product
Q41: Which of the following is true about
Q42: Design specification limits are also known as
Q43: It is common for companies to aim
Q44: As a rule of thumb,to do a
Q45: Which of the following statements is correct?
A)A
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents