A Line Tracking the Project Costs Over the Life of the Project

Question 81

Multiple Choice

A line tracking the project costs over the life of the project ______.


A) is known as the P-curve because the line represents projected costs
B) is known as the E-curve because the line curves sharply from bottom left to top right
C) is known as the S-curve because the line is shaped like the letter S
D) is known as the S-curve because the line represents scheduled costs

Correct Answer:

verifed

Verified