At a merge point,______.
A) the largest preceding EF becomes the ES for that node
B) the largest preceding ES becomes the EF for that node
C) the smallest preceding EF becomes the ES for that node
D) the smallest preceding ES becomes the EF for that node
Correct Answer:
Verified
Q58: In the AON method,_.
A)the node represents the
Q59: Early finish time (EF)_.
A)is the earliest possible
Q60: Which of the following is a limitation
Q61: "Crashing" a project _.
A)is speeding up a
Q62: A critical path consists of _.
A)activities that
Q64: The backward pass _.
A)starts at the end
Q65: At a burst point,_.
A)you have a node
Q66: In considering the impact supply chains have
Q67: Which of the following statements is true
Q68: Which of the following is an appropriate