Which is the critical path in the following?
A) Path 1 takes 18 days.
B) Path 2 takes 14 days.
C) Path 3 takes 22 days.
D) Path 4 takes 16 day.
Correct Answer:
Verified
Q64: The backward pass _.
A)starts at the end
Q65: At a burst point,_.
A)you have a node
Q66: In considering the impact supply chains have
Q67: Which of the following statements is true
Q68: Which of the following is an appropriate
Q70: In managing projects in supply chains,working with
Q71: Which of the following is NOT true
Q72: The forward pass method allows us to
Q73: If an estimate for an activity is
Q74: A merge point refers to _.
A)a node