The main outputs of which process include a risk register, risk report, and project documents updates?
A) identifying risks
B) planning risk management
C) planning risk response
D) monitoring risk
Correct Answer:
Verified
Q32: Which is a fact-finding technique that can
Q33: Which process involves monitoring identified and residual
Q34: What is the first step in a
Q35: Which process involves determining what risks are
Q36: Which process involves prioritizing risks based on
Q38: Which process involves taking steps to enhance
Q39: What process involves deciding how to approach
Q40: _ are predefined actions that the project
Q41: Which action involves reducing the impact of
Q42: The term _ is used to describe