Which Is True of the Schedule Performance Index (SPI)

Question 62

Multiple Choice
 Which is true of the schedule performance index (SPI)?
A) It can be used to estimate the projected time to complete the project.
B) It means that a project is behind schedule if an SPI is greater than one.
C) It means that a project is ahead of schedule if SPI is lesser than one or hundred percent.
D) It is the ratio of planned value to actual costs.

 Which is true of the schedule performance index (SPI) ?


A) It can be used to estimate the projected time to complete the project.
B) It means that a project is behind schedule if an SPI is greater than one.
C) It means that a project is ahead of schedule if SPI is lesser than one or hundred percent.
D) It is the ratio of planned value to actual costs.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents