Which is true of the schedule performance index (SPI) ?
A) It can be used to estimate the projected time to complete the project.
B) It means that a project is behind schedule if an SPI is greater than one.
C) It means that a project is ahead of schedule if SPI is lesser than one or hundred percent.
D) It is the ratio of planned value to actual costs.
Correct Answer:
Verified
Q57: Which statement is true of analogous estimates?
A)
Q58: Which type of estimating uses project characteristics
Q59: Good Earth, a company manufacturing packaged food
Q60: What term is used for analogous estimates?
A)
Q61: _ costing considers the total cost of
Q63: _ costing helps to see a big-picture
Q64: Which statement best defines cost variance?
A) planned
Q65: The main goal of which process is
Q66: _ theory states that when many items
Q67: What is the purpose of a cost
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents