What Is an Accurate Difference Between the Program Evaluation and Review

Question 77

Multiple Choice
 What is an accurate difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM)?
A) CPM addresses the risk associated with duration estimates whereas PERT does not.
B) Unlike CPM, PERT estimates only when there is no risk of uncertainty.
C) CPM involves more work than PERT because it requires several duration estimates.
D) PERT uses different duration estimates whereas CPM uses one specific duration estimate.

 What is an accurate difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) ?


A) CPM addresses the risk associated with duration estimates whereas PERT does not.
B) Unlike CPM, PERT estimates only when there is no risk of uncertainty.
C) CPM involves more work than PERT because it requires several duration estimates.
D) PERT uses different duration estimates whereas CPM uses one specific duration estimate.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents