After Working with Key Stakeholders to Define Activities and Calculate

Question 59

Multiple Choice
 After working with key stakeholders to define activities and calculate their resources, what is the next process in project schedule management?
A) develop the schedule.
B) control the schedule.
C) determine their dependencies.
D) estimate the duration of activities.

 After working with key stakeholders to define activities and calculate their resources, what is the next process in project schedule management?


A) develop the schedule.
B) control the schedule.
C) determine their dependencies.
D) estimate the duration of activities.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents