In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.
Correct Answer:
Verified
Q10: An activity is an element of work
Q11: A Tracking Gantt chart is based on
Q12: In project schedule management, the next step
Q13: A dependency pertains to the sequencing of
Q14: In a Gantt chart, thick black bars
Q16: After defining project activities, the next step
Q17: The arrows in a network diagram represent
Q18: Project schedules grow out of basic documents
Q19: Network diagrams are the preferred technique for
Q20: It is important for the activity list