Which of the Following Best Describes a Kill Point in the Project

Question 45

Multiple Choice
 Which of the following best describes a kill point in the project life cycle?
A) The period of time given to managers during the feasibility phases to decide on the cost, quality, and time constraints for the project
B) A review of the status of a project at each phase of development to determine if it should be continued, redirected, or terminated
C) The point of time in the project lifecycle after which it is impossible to terminate a running project
D) The final submission of the project deliverables after which the project is terminated

 Which of the following best describes a kill point in the project life cycle?


A) The period of time given to managers during the feasibility phases to decide on the cost, quality, and time constraints for the project
B) A review of the status of a project at each phase of development to determine if it should be continued, redirected, or terminated
C) The point of time in the project lifecycle after which it is impossible to terminate a running project
D) The final submission of the project deliverables after which the project is terminated

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents