Basic reasons for creating dependencies of project activities include each of the followingexcept
A) external dependencies.
B) discretionary dependencies.
C) desirable dependencies.
D) mandatory dependencies.
Correct Answer:
Verified
Q53: When working with project management software,factors that
Q54: The shortest time in which an activity
Q55: Which of the following is used to
Q56: Dependencies defined by the project team are
A)discretionary
Q57: The amount of time that an activity
Q59: If prototype testing can be started only
Q60: Dependencies involving relationships between the project and
Q61: A method of planning and managing projects
Q62: Which of the following includes activities performed
Q63: Shortening an activity is called
A)float.
B)crash.
C)reduction.
D)smoothing.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents