One unit of product A is made of two units of B and four units of C.B is made of two units of D and three units of E.C is made of three units of D and two units of F.A,C,D,and E have lead times of one week,and B and F have lead times of two weeks.If 100 units of A are required in week 5,develop the material requirements plan specifying when items are to be ordered and received.There are no units of inventory on hand.Hint: Since there are no units of inventory on hand,gross requirements will be equal to net requirements. 100 units of A should be ordered in the fourth week because these units are needed in the fifth week and the lead time is one week.
Correct Answer:
Verified
100 units of A would require 200 units...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q103: One unit of product A is made
Q104: What is CRP?
Q105: What is regeneration MRP?
Q106: What are the two approaches for updating
Q107: How does APICS define the BOM?
Q109: What are the three inputs to MRP?
Q110: Complete the following material requirements plan for
Q111: Complete the following material requirements plan for
Q112: What is "coding" used for in MRP?
Q113: One unit of product A is made
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents