One of the worst systemic problems that MRP faces is
A) lack of commitment by management.
B) sudden cancellation of sales.
C) last-minute changes in order sizes.
D) lack of computer time.
E) both b and c
Correct Answer:
Verified
Q59: The first book on MRP was written
Q60: Demand for an item has to be
Q61: _ lists the key resources needed to
Q62: What is a thorough,time-demanding method of updating
Q63: _ is the function of establishing,measuring,and adjusting
Q65: _ is the essence of supply chain
Q66: In a _ model the idea is
Q67: What information system would require current data
Q68: Closed-loop MRP consists of
A)production planning.
B)master production scheduling.
C)capacity
Q69: MRP record processing proceeds from one level