Question 140

Multiple Choice

In order to build spas ready to be installed, there are only about six tasks that have to be completed. An operations manager determines how long it will take to complete each of these tasks. What scheduling device would be most appropriate for this relatively uncomplicated manufacturing process?


A) Gantt chart
B) Enterprise materials planning
C) Critical path assessment
D) Statistical process control
E) Flexible manufacturing diagram