____ Change Orders Are Oral or Written Acts or Omissions

Question 70

Multiple Choice

____ change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.


A) Virtual
B) Non-binding
C) Apparent
D) Constructive

Correct Answer: