Question 31

Multiple Choice
Jalbert Incorporated planned to use materials of $11 per unit but actually used materials of $15 per unit, and planned to make 1,560 units but actually made 1,730 units.
The flexible-budget amount for materials is ________.
A) $17,160
B) $23,400
C) $19,030
D) $25,950

Jalbert Incorporated planned to use materials of $11 per unit but actually used materials of $15 per unit, and planned to make 1,560 units but actually made 1,730 units.
The flexible-budget amount for materials is ________.


A) $17,160
B) $23,400
C) $19,030
D) $25,950

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents