Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. If Bob were 100 percent available to work on task R during the entire five days, his efficiency rate is __________%.
Correct Answer:
Verified
Q21: If the appropriate scheduling equation for task
Q22: The use of _ activity time estimates
Q23: Three important parameters used to assess the
Q24: When we change technology, we may also
Q26: The _ approach to constrained resource scheduling
Q26: _ times result from an attempt to
Q27: _ aims to minimize the period-by-period variations
Q28: Given a scheduling equation W = D
Q29: _ describes the amounts of individual resources
Q30: With respect to project scheduling, _ is