Using Precedence Diagramming Methods, Activity B Must Not Start Until

Question 28

Short Answer

Using precedence diagramming methods, activity B must not start until after activity A has been completed. Moreover, the outcome of activity A cannot be used until 3 days after its completion. This relationship between activities A and B is an example of a(n)__________.

Correct Answer:

verifed

Verified

finish to ...