Project task E has the following estimates: (1)optimistic time - 10 days, (2)Pessimistic time - 20 days, and (3)Most likely time - 12 Days. The standard deviation for time using the beta statistical distribution is ________ days.
Correct Answer:
Verified
Q31: The arrangement of all activities (and, in
Q32: Any time two or more paths of
Q33: The authors, when discussing networks, describe a(n)_
Q34: Project task E has the following estimates:
Q35: Task H has duration of 5 days,
Q37: _ is an obvious way to check
Q38: The _ chart shows planned and actual
Q39: In CPM(PDM), an activity can be conducted
Q40: Assume that task J has a most
Q44: Describe the process for determining the critical