Which of the Following Statement(s)concerning Probabilities of Completion Is/are Incorrect

Question 12

Multiple Choice

Which of the following statement(s) concerning probabilities of completion is/are incorrect?


A) Using the variance of each activity,we can compute the likelihood of completing the project in a given time period.
B) The probability of completing a path is found by calculating the standard normal deviate of the desired completion time less the expected completion time.
C) The distribution of a path's completion time will be approximately normally distributed if the path has a large number of activities on it.
D) The individual activity completion times must be normally distributed
E) All of the above are incorrect

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents