Jim contracted with Kevin to serve as a guide for Kevin on his three-week fishing trip to Canada.The contract was made on April 1 with the trip to begin on June 1.On May 1, Kevin notified Jim that he had changed his mind and would be unable to make the trip.He also refused to pay Jim any compensation.In this situation:


A) because the contract is executory, Jim has suffered no damages, and Kevin has no obligation to pay any compensation.
B) Kevin has anticipatorily repudiated the contract and is liable to Jim for damages.
C) Jim may wait until June 1 to see if Kevin will perform his contractual duties and, if he does not, there is a material breach.
D) both (b) and (c) above are correct.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents