What is a function point?
A) a chart that shows tasks,dates,and dependencies in a project schedule
B) a feature or function of the new program
C) a hierarchy of the tasks required to complete a project
D) the sequence of activities that determines the earliest date by which the project can be completed
Correct Answer:
Verified
Q112: The _ is the sequence of activities
Q113: What is systems development? Why is it
Q114: The main problem of the SDLC approach
Q115: The term _ refers to a set
Q116: Function points as an estimating technique for
Q118: Project teams create a(n)_,which is a hierarchy
Q119: Which of the following is a characteristic
Q120: A _ shows the tasks,start and finish
Q121: Describe the composition of a development team.
Q122: Explain the importance of configuration control.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents