Which of the following is NOT a primary mechanism by which the PM exerts control?
A) reviews
B) personnel assignments
C) audit reports
D) resource allocation
E) all of the above are mechanisms by which the PM exerts control
Correct Answer:
Verified
Q12: The plan-monitor-control cycle constitutes a "closed loop"
Q27: Remarks should be directly attributed to individuals
Q29: According to the text, there is no
Q30: Which of the following is NOT an
Q31: The percentage of an activity's budget actually
Q32: Exception reports are prepared to disseminate the
Q36: To maximize efficiency, project team meetings should
Q37: Earned value is a measure for overall
Q38: Exception reports are primarily intended for unexpected
Q40: Project review meetings are always important.