A metric that provides an estimate for completing the scheduled work that remains once the project is started is called the
A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
Correct Answer:
Verified
Q32: The budgeted cost of work scheduled for
Q33: Cost Variance (CV) is _
A) how much
Q34: Earned Value tells us _
A) how much
Q35: Expected Time to Completion (ETC) is _
A)
Q36: Barring a change in project scope and
Q38: Actual Cost (AC) is _
A) how much
Q39: If we know the Actual Cost of
Q40: Estimate at Completion (EAC) is _
A) how
Q41: Describe how the SPI and CPI can
Q42: What is a project review and what
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents