Under the Precedence Diagramming Method, the least common relationship between two activities which occurs when they must complete at the same time is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Correct Answer:
Verified
Q46: Once the project schedule and project budget
Q47: Critical Chain Project Management (CCPM) is based
Q48: Define predecessor, successor, and parallel activities.Give a
Q49: Scheduling other projects so that resources may
Q50: Rent, utilities, insurance and administrative costs are
Q52: The cost of labor for using a
Q53: The final step in determining the cost
Q54: Installing the operating system on a computer
Q55: Many organizations have a kick-off meeting because
A)
Q56: To make a decision to attempt to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents