Under the Precedence Diagramming Method, the most common relationship between two activities which implies a logical sequence is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these