Once the project schedule and budget are accepted by the client or sponsor, the project plan becomes the baseline plan that will be used as a benchmark to track the project's actual progress.
Correct Answer:
Verified
Q1: Identifying the critical path is important because
Q2: The direct costs of using a resource
Q3: A parallel activity is a task that
Q5: A start-to-finish activity is the most common
Q6: Project network diagrams provide valuable information about
Q7: The critical path has zero slack (or
Q8: Predecessor activities are activities that must be
Q9: A reserve can provide a cushion when
Q10: Installing a server before loading the operating
Q11: Start-to-Start and Finish-to-Finish relationships allow activities to