Which of the following statements is MOST correct?
A) If a project's internal rate of return (IRR) exceeds the required return, then the project's net present value (NPV) must be negative.
B) If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
C) The IRR calculation implicitly assumes that all cash flows are reinvested at a rate of return equal to the IRR.
D) A project with a NPV = 0 is not acceptable.
Correct Answer:
Verified
Q43: Any project deemed acceptable using the discounted
Q44: Many financial managers believe the payback period
Q45: If a project has multiple internal rates
Q46: If a project is acceptable using the
Q47: If a project is acceptable using the
Q49: Calculating the modified internal rate of return
Q50: A project with a NPV of zero
Q51: Because the MIRR assumes reinvestment at the
Q52: The capital budgeting manager for XYZ Corporation,a
Q53: Project Alpha has an internal rate of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents