A scheduling rule used for sequencing jobs through two work centers such that makespan is minimized is:
A) critical ratio rule.
B) Johnson's rulE.
C) slack per operation rule.
D) shortest processing time rule.
E) Pareto rule.
Correct Answer:
Verified