A manager is trying to estimate the appropriate learning curve for a certain job. The manager notes that the first four units had a total time of 30 minutes. Which learning curve would yield approximately this result if the first unit took 10 minutes?
A) .70
B) .75
C) .80
D) .85
E) .90
Correct Answer:
Verified