A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers perform this task five times. The observations were made in an air-conditioned, well-lighted training facility, at ground level, with all tools and equipment clean and readily available.
a. What is the actual average time for this task?
b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers?
c. What is standard time for this task if allowances are 8% constant and 6% variable?
d. If the analyst then thought more carefully about his experiment, and decided that the variable allowances needed to be increased to match the real (outside, unair-conditioned) work environment, and that the proper variable allowance was not 6% but 12%, what is the revised standard time?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q181: A manufacturing plant is trying to determine
Q182: The data in the following table
Q183: The data in the following table
Q184: A task involves positioning two metal
Q185: What is the required sample size to
Q186: An operation in a television factory has
Q188: Suppose that an analyst takes 50 samples
Q189: A manufacturing plant assembly line job has
Q190: A grocery store is trying to determine
Q191: An initial analysis of a laboratory
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents