Solved

The First Unit of a Product Took 80 Work Days

Question 60

Multiple Choice

The first unit of a product took 80 work days. The learning curve is estimated to be 90%. The time for the fourth unit will be about __________ work days and the time for the first four units will be about __________ work days.


A) 51; 250
B) 250; 51
C) 65; 285
D) 51; cannot be determined
E) 65; cannot be determined

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents