Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
a. What is the crash cost per unit time for activity A?
b. What is the crash cost per unit time for activity B?
c. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
d. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
e. Assuming no other paths become critical, how much can this project be shortened at what total added cost?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q46: The network analysis method that allows activity
Q61: Explain why the critical path is the
Q66: What are the earliest activity start time
Q97: _ is a network technique using only
Q98: _ divides a project into more and
Q101: Given the project within the table
Q104: Briefly describe the concept of cost/time trade-off
Q105: The network below represents a project being
Q106: A network consists of the following
Q114: Describe in words how to calculate a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents