A flood will require mining operations to cease for at least six months.How would a force majeure clause affect the legal status of the miner's obligations relating to its existing supply contracts?
A) non-performance of the contract will be excused without liability
B) the innocent party will have the right to terminate and sue for breach
C) performance obligations will be suspended until a specified event occurs
D) the innocent party will have the right to sue for damages for breach
Correct Answer:
Verified
Q11: Which of the following would disentitle a
Q12: Which statement describes a distinguishing feature of
Q13: Why did the Supreme Court of Canada
Q14: A courier employed by Jack's Deliveries delivered
Q15: Rumie paid a $5000 retainer to a
Q17: Which of the following is a distinguishing
Q18: Randall was wrongfully dismissed from his job
Q19: Which term best describes damages that award
Q20: Margo has agreed to purchase a used
Q21: In which situation might a court be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents