Which of the following is the estimate of the time that will be needed to perform the task?
A) estimated duration
B) optimistic duration
C) pessimistic duration
D) expected duration
E) none of these
Correct Answer:
Verified
Q57: A strategy wherein all project stakeholders participate
Q58: Which of the following is NOT one
Q59: Elapsed time takes into account which of
Q60: Which of the following is the estimate
Q61: Which of the following is the estimate
Q63: Which of the following is considered a
Q64: Which of the following is NOT one
Q65: Which of the following is the sequence
Q66: Which of the following is NOT shown
Q67: Which of the following is the amount
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents