Two workers, A and B, perform sequential tasks on a balanced line producing wooden bookcases. Worker B applies a spray coating of paint primer to shelves that Worker A has sanded. Worker A can only sand one shelf at a time while Worker B is able to apply the spray primer to four shelves simultaneously. In order to keep the line balanced:
A) Output of Worker A will need to be stored in four-piece kanbans.
B) Output of Worker B will need to be stored in four-piece kanbans.
C) Worker B will necessarily experience idle capacity.
D) Worker A will be required to produce a large batch of in-process inventory.
Correct Answer:
Verified
Q38: The practice called "backflush costing" only charges
Q39: Throughput time is most likely to be
Q40: Just-in-time management reduces total throughput time by:
A)
Q41: According to the Theory of Constraints, all
Q42: Producing under the Theory of Constraints is
Q43: A kanban, or small buffer stock, is
Q45: Two machines, A and B, are arranged
Q46: Clean and Shiny, LLC, provides window cleaning
Q47: True Vision Cable Systems, Inc., employs activity-based
Q48: Everything U Need is the campus store
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents