-Using the Data Above on Five Orders, Compute the Shortest

Question 28

Multiple Choice

Order  Processing TimeDue Date1592333454513567\begin{array}{ccc} \text {Order }&\text { Processing Time} & \text {Due Date} \\1 & 5 & 9 \\2 & 3 & 3 \\3 & 4 & 5 \\4 & 5 & 13 \\5 & 6 & 7\end{array}
-Using the data above on five orders, compute the shortest processing time (SPT) sequence.


A) 2,3,1,4,5
B) 1,2,3,4,5
C) 2,3,5,1,4
D) 2,5,4,1,3

Correct Answer: