Copenhagen Industries uses a kanban system to manage production of their subassembly. In a 10-hour day, they use 1,500 units and use containers that can hold 50 units each. It takes 45 minutes to fill and move a container of parts to the right place on the subassembly line that is currently rated at a 15% safety factor.
-How many containers should the kanban system of Copenhagen Industries be using?
A) 26
B) 82
C) 155
D) 9
E) 3
Correct Answer:
Verified
Q16: An integrated electronic-chip manufacturer has a demand
Q17: Berlin Industries uses a kanban system to
Q18: Berlin Industries uses a kanban system to
Q19: Berlin Industries uses a kanban system to
Q20: Berlin Industries uses a kanban system to
Q22: Copenhagen Industries uses a kanban system to
Q23: Copenhagen Industries uses a kanban system to
Q24: Copenhagen Industries uses a kanban system to
Q25: Copenhagen Industries uses a kanban system to
Q26: Istanbul Industries uses a kanban system to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents