Question 35

Multiple Choice

Adrian, a scrum master for the company's new project, organized product features by priority and has assembled the list of what the core development team will work on during the next iteration. What scrum artifact is the appropriate item for this list of current tasks for the development team?


A) Product backlog
B) Sprint backlog
C) Product increment
D) All of these answer choices are correct.