During the analysis stage of the SDLC, business requirements for a project are determined by
A) the IT steering committee reviewing the feasibility study.
B) systems analysts meeting with end users.
C) the lead system analyst reviewing the project plan.
D) All of these answer choices are correct.
Correct Answer: