Multi-process handling occurs when one worker is performing more than one processing task with or without machines. What is the highest process risk in this type of environment?
A) Excessive wear and tear on the equipment.
B) Employee burnout or loss of engagement
C) The risk of ergonomic injury.
D) The risk of increased variability in the output of the process.
Correct Answer:
Verified
Q17: Lean practitioners wanting to enact empiricism into
Q18: Which principle used in lean would allow
Q19: Quality at the source is a principle
Q20: One of the many principles of process
Q21: The second part of Jidoka includes separating
Q23: Using a self-detection method in the reduction
Q24: The stop and fix method is one
Q25: Integrating improvements within the organization is best
Q26: Kaizen is a Japanese word meaning "change
Q27: Kaikaku is used for breakthrough continuous improvement.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents