Which of the following would you find in a Quality Management Plan rather than a Quality Management Strategy?
A) Criteria to assess programme success
B) Resource requirements for quality management
C) Guidelines to ensure the appropriate use of audits and health checks
D) Plans and dates for audits and reviews
Correct Answer: